WSJ+
WSJ EnterprisesSign in
← All of the platform

Watch a single job move through it

The claim that this is one system rather than four is easy to make and easy to check. Below is one job, start to finish: the estimate that became the budget, a day on site, the question that came out of it, the change order that answered it, and the cost table that moved as a result.

Ridgeline Materials — Plant 2 Expansion24-118 · Concrete & masonry package · Lafayette, Alabama
01EstimateEST-24-118Won
Concrete & masonry package4 sections
03-300 Cast-in-place concrete$612,000
04-200 Unit masonry$398,500
03-200 Reinforcing steel$186,000
01-500 Temporary facilities$88,000
Proposal total$1,284,500

Accepted, and it becomes the project's original budget — not retyped into one.

02Daily reportDR-0142Submitted
Tue 16 Sep 202684°F, partly cloudy18 craft
9
Concrete
6
Masonry
3
Laborers

Placed 214 CY at Bay 4 slab-on-grade. Set forms for equipment pads E-7 through E-11. Masonry crew continued CMU at the north wall, course 14.

Filed from the job. The office reads this one, not a retyped copy of it.

03RFIRFI-017Answered
Equipment pad E-9 conflicts with trench drainagainst S-204

Asked

Pad E-9 as dimensioned on S-204 lands on the trench drain run shown on P-110. Confirm whether the pad shifts east or the drain reroutes.

Answered

Shift pads E-9 through E-11 east by 2'-4" and thicken to 12". Drain run is unchanged. Issue as a change order.

  1. Raised from the field17 Sep, 7:42am
  2. Sent to the design team17 Sep, 9:15am
  3. Answered19 Sep, 4:03pm
  4. Priced as CO-00422 Sep
04Change orderCO-004Approved
Equipment pads E-9 to E-11 — relocate and thickenfrom RFI-017
Additional concrete, 34 CY$17,340
Forming and reinforcing$14,880
Layout and survey$6,500
Approved 24 Sep 2026+$38,720

Approving it moves the budget below. There is no second spreadsheet to update.

05Job cost24-118Live
Original budget
$1,284,500
Revised (+$38,720)
$1,323,220
Committed
$1,147,900
Actual to date
$902,455
Cost codeBudgetCommittedActual
03-300 Cast-in-place concrete$650,720$588,400$471,220
04-200 Unit masonry$398,500$351,000$268,905
03-200 Reinforcing steel$186,000$172,500$141,330
01-500 Temporary facilities$88,000$36,000$21,000

Forecast at completion $1,318,000 — $5,220 under the revised budget. The $38,720 from CO-004 landed on 03-300, because that is where the work happened.

Illustrative example. Project, people and figures are invented.

A product of WSJ Enterprises, LLC · 1283 County Road 75, Lafayette, Alabama

TermsPrivacy[email protected]