The moneyBudgets
Original, plus every approved change
The original budget and every approved adjustment to it, held by cost code. One screen shows what is left, which lines are over and by how much, and what moved the budget since it was locked.
Workflow
Follow the concrete line
Line 03300 on the Ridgeline demo job, cast-in-place concrete, which ran over after the pad relocation and was partly covered by a transfer from paving. The demo is live: click a line, switch views or search.
The tour plays on its own · click any line to explore
Reading it
How to read a line
Every line in the ledger has a burn bar, and the selected line gets a waterfall in 04 Line. The figures follow three rules.
03390Curing and sealing58.4%
03350Concrete finishing83.9%
03300Cast-in-place concrete107.5%
02370Erosion controlno budget
Actual costCommittedRevised budgetOver, past the tick
Revised$759,340
less Actual−$603,800
less Committed−$212,600
Remaining($57,060)
—Zero is an em dash. Most of a budget grid is zeroes, and a dash says so without having to be read.
($57,060)Negatives take parentheses. A minus sign can be lost at a column edge; brackets can’t.
$759,340No cents in the grid. They stay on each transaction, in the drawer, where they matter.